Full logistic scope for mobilization cable laying barge in Eemshaven
02 June 2022
Ports & terminals

Full logistic scope for mobilization cable laying barge in Eemshaven

Based on a long term contract with NKT, Wagenborg started the mobilization project of a cable laying barge in Eemshaven. This project includes the full logistic scope of the mobilization.

Within a time frame of seven weeks three barges will be connected and mobilized as one single cable laying barge. In addition another barge will be equipped with a cable tank.

One stop shop for cable logistics and storage

With this project, Wagenborg again proves her added value in Eemshaven to the offshore wind industry. The combination of the Wagenborg in-house customs and agency services, crane rentals, towage services and an own shipyard result in cost-efficient mobilization projects: a one stop shop for cable logistics and storage.

Terminal Eemshaven

The mobilization takes place at the Wagenborg terminal in Eemshaven. This terminal has a storage area of ??160,000 square meters and a quay length of over 1.500 meters. Its modern facilities and privileged location make it a popular base port for offshore wind projects. Wagenborg terminal Eemshaven has already supported various offshore windfarms in the North Sea with port logistic services.